August 26th. JR Christensen family rented us their backhoe and Chris and his sons Jared and Aaron placed the boulders around the walkout/basement patio. It took ~ two days as I recall.
The roof is on in this photo. The roofers took two days -- and probably would have been finished in one if they had brought more roofing paper. The wind had ripped off the paper in a few places and it had to be replaced before they could shingle.
After debating shingle color for months, we selected Tamko Heritage 30 "Weathered Wood". We considered GAF/Elk's "Cool Color Series" but ultimately decided against. Like many "green" or "energy efficient" ideas we've explored it came down to cost/benefit analysis. They have a higher reflective index than regular asphalt shingles. However, they cost ~50% more than regular shingles, and wouldn't save enough in energy costs to pay for themselves within the lifetime of the shingle. If someone had an unlimited budget, or stricter ideals... but regrettably with us it has to be practical.